DPG Document No. _____________
ENVIRONMENTAL ASSESSMENT
FOR
CONSTRUCTION AND OPERATION
OF THE
INSENSITIVE MUNITIONS (IM)
TEST GRID
AT
GARY H. RICHINS
MICHAEL M. ROBINSON
Environmental Technology
Office
February
2006
Environmental Technology Office
SIGNATURE PAGE
|
PREPARED BY: |
REVIEWED BY: |
|
GARY H. RICHINS Date Environmental
Protection Specialist Environmental
Technology Office |
________________________________ KATHLEEN E.
CALLISTER Date Environmental Coordinator Environmental
Technology Office |
|
SECURITY CHECK: WAYNE RINDLISBACHER Date Chief,
Counterintelligence Office |
JIMMIE W. BARNETT Date Chief, Munitions and
Obscurants Division |
|
|
PROPONENT: |
|
CONCUR: |
DOUGLAS A.
TAMILIO Date LTC, IN Commanding, West
Desert Test Center |
|
MARION M. FORD Date Environmental
Coordinator Directorate of
Environmental Programs |
APPROVAL: |
|
|
GREG D. OLSON Date Commanding |
TABLE OF CONTENTS
PAGE
1.
PURPOSE AND NEED FOR ACTION
.1
2. DESCRIPTION OF THE PROPOSED
ACTION
.2
3. ALTERNATIVES INCLUDING THE PROPOSED ACTION
..4
4. AFFECTED ENVIRONMENT
..10
5. ENVIRONMENTAL CONSEQUENCES
12
6. LIST OF PREPARERS,
AGENCIES AND PERSONS CONSULTED
..16
7. REFERENCES..
.18
1.1. The Munitions
and Obscurants Division (MOD) within the West Desert Test Center (WDTC) at United
States (U.S.) Army Dugway Proving Ground (DPG) has long conducted testing on a
wide variety of conventional military munitions. Section 2.1.5.3 of the Final
Environmental Impact Statement for Activities Associated with Future Programs
at U.S. Army Dugway Proving Ground, (
1.2. About
four years ago (2001), a congressional mandate expanded the IM testing
requirement to include all munitions in the military inventory. Within U.S. Department of Defense (DoD), initiation
of the bulk of this required testing has been delayed until it has become a
time sensitive issue. According to one DoD official at a the DPG
Commanders Conference (July 2005),
there is great need within DoD to do this
testing
. This newly mandated
requirement provides a unique opportunity for DPG to expand its IM testing role
at WDTC to fill this DoD need if a facility of sufficient size and capability
can be provided.
1.3. Past IM
testing at WDTC has been conducted at the RADPAD located southwest of Carr
Area. The newest IM test guidelines (MIL-STD-2105
C and TB 700-2) require that when a tested munition is detonated, each of the
fragments must be located, mapped and recovered. This requires a relatively flat, cleared area
that exceeds the blast radius of the particular munition being subjected to IM
testing. Some of the munitions presently
undergoing IM testing at WDTC have a potential blast radius of about 500
feet. The RADPAD only allows a blast
radius of about 300 feet and, due to its design and location, cannot be
practically expanded. The maximum blast radius required for IM testing of
presently fielded conventional munitions in the military inventory would be
approximately 2000 feet according to a January 2005 Department of Defense
Explosives Safety Board (DDESB) briefing by John Tatum and Mike Swisdak from
A-P-T Research in Huntsville, AL. This potential future requirement cannot be
met at the RADPAD, therefore MOD is seeking to establish a designated IM Test
Grid on the northern part of the former V-Grid location north of
CHAPTER 2 DESCRIPTION OF THE PROPOSED ACTION
2.1. The
proposed action is to design, construct, and operate a designated IM Test Grid
at the former V-Grid location (see map on Page 3). The proposed facility would provide the space
and capability for MOD to conduct the required IM testing on all conventional
munitions presently in the military inventory at a single location at WDTC.
2.2 Military
and Government Agency tests, training exercises, tactical maneuvers, weapons
qualification, gunnery tables, munitions testing, and test and training
facility construction projects have been successfully conducted at DPG for over fifty years. However, DOD and
2.3. Work on
this EA was initiated by holding an internal DPG Scoping Meeting on

CHAPTER
3 ALTERNATIVES INCLUDING THE PROPOSED ACTION
3.1. This
chapter describes the criteria used for comparing the various alternatives, the
alternatives including the proposed action, and the application of these
criteria to the process of selecting the proposed action.
3.2. Selection
Criteria
3.2.1. Sufficient
Size: The area selected for the proposed
action must be of sufficient size to allow IM testing of all conventional
munitions in the military arsenal, now and in the foreseeable future. This must include a relatively flat, circular,
cleared area, expandable to a 2000-foot radius, to allow fragment documentation
and retrieval.
3.2.2. DPG/WDTC Command Approval and Support. The selected area for the proposed action
must have the approval and support of both the DPG Commander and the WDTC
Commander. In 2002, MOD met with both
Col. Harter (DPG commander at the time) and LTC Rasmussen (WDTC commander at
the time) to discuss the need for an expanded, dedicated IM Test facility to
meet the DoD requirement for increased IM testing of all conventional munitions
in the military arsenal. MOD was
directed to look at areas on either side of the active WDTC test areas (where
outdoor stimulant testing is conducted).
MOD met with LTC Tamilio (the present WDTC commander) in an Initial
Command Review (ICR) in October 2004 and
was directed to go ahead with the necessary approval process for setting up the
proposed IM Test Grid. The proposed
action was presented to the RPPB and approved on
3.2.3. Cost to
Upgrade. Cost to upgrade the area selected for the proposed action must be
acceptable to MOD and compatible with customer budgetary and time constraints.
3.2.4.
Serviceable Command Post (CP).
The nature of IM testing requires that the area selected for the
proposed action have a serviceable, instrumented, and strategically located
command post from which to oversee the IM testing process.
3.2.5.
Electrical, Communication and Data Connections. Where possible, the area selected for the
proposed action should have electrical, communication and data lines available
at, or in close proximity to, the CP location.
3.2.6.
Adequate Roads. The area selected
for the proposed action must have adequate roads that are passable in all
seasons.
3.2.7.
Controlled Access During IM Testing.
For safety reasons, the area selected for the proposed action must be
able to have access easily controlled during actual IM testing.
3.2.8.
Proximity to and Compatibility with other Tests and Test Facilities. The
area selected for the proposed action must be sufficiently far from other test
areas to allow both areas to be used concurrently. In addition, the selected area must be
compatible with other test activities that have a need to use the area. Long-term coordination and communication would
be necessary to avoid and resolve conflicts between planned tests before they
occur.
3.2.9. Natural
Resource Concerns. The area selected
must have no over-riding natural resource concerns that would preclude its use as
the location for the proposed action.
3.2.10.
Cultural Resource Concerns. The
area selected must have no over-riding cultural resource concerns that would
preclude its use as the location for the proposed action.
3.2.11. Security
for Classified IM Tests. The area
selected for the proposed action must be able to be secured for possible future
classified IM tests.
3.2.12.
Regulatory/Permit Concerns. The
area selected for the proposed action must have no incompatible or over-riding
State or federal environmental permit concerns.
3.3. Alternatives.
3.3.1. Alternative A:
No Action: Do not approve design, construction, and operation of a new
IM Test Grid.
3.3.1.1. Non-approval of the design, construction,
and operation of the IM Test Grid at WDTC would mean that the IM testing of
conventional military munitions would continue at the same location (RADPAD)
and at the same level as at present.
3.3.1.2. Due to its design and location the RADPAD
cannot be expanded or improved to accommodate the new IM testing requirements.
3.3.1.3. This alternative is not responsive to the
increasing opportunity for IM testing offered by the DoD-wide implementation of
MIL-STD-2105 C and TB 700-2 . This
alternative is not in the best interest of the defense of the
3.3.1.4. The no action alternative would not have any
different environmental consequences than current operations. However, it would not achieve current
national defense objectives and IM testing requirements. The no action
alternative would not increase WDTC and MOD testing capabilities.
2.3.2. Alternative B.
Approve the design, construction and operation of a new IM test grid on
the playa/mudflats west of
3.3.2.1. These two generalized playa/mudflat areas
were initially attractive because they have large, relatively flat areas that
are devoid of vegetation.
3.3.2.2. These two generalized playa/mudflat areas
were removed from further consideration after recognizing:
·
Roads were
inadequate or nonexistent and were seasonally restricted.
·
No CP was
available.
·
Required
electrical, communication, and data lines were unavailable.
·
Upgrading any of
the playa/mudflat sites to an acceptable standard could not be accomplished in
a timely manner and would be cost prohibitive.
3.3.3. Alternative C.
Approve the design, construction and operation of a new IM test grid on
the Dugway Thermal Treatment Facility (DTTF)[formerly Open Burn-Open Detonation
(OBOD)] site south of Carr Area.
3.3.3.1. The DTTF was initially attractive because:
·
A large cleared
area of sufficient size already exists.
·
Although a CP
would have to be constructed and electrical, communication, and data lines
would have to be improved, the cost to upgrade the facility would likely be acceptable.
·
The DTTF has no
natural resource or cultural resource concerns.
3.3.3.2. The DTTF was removed from further
consideration because:
·
A potential
security risk for possible future classified IM testing exists due to the close
proximity of the DTTF to the eastern DPG boundary and off-post public access
areas.
·
A continued
concern over regulatory and permitting issues.
These concerns stem from the fact that the DTTF is regulated as a
provisional Treatment Storage and Disposal (TSD) facility under the Resource
Conservation and Recovery Act (RCRA) interim status standards at 40 CFR part
265 and 40 CFR 270.71 (a) (1)(2)(3). DPG
Directorate of Environmental Programs (DEP) and Utah Division of Solid and
Hazardous Waste (UDSHW) have expressed the opinion that testing should not be
allowed on the DTTF [28 November 2005 e-mail from John Bate (DEP) to Gary
Richins (WD-EN) and others.]
3.3.4.
Alternative D: The proposed
action of this EA is to design, construct, and operate a designated IM Test
Grid at the former V-Grid location (see map on Page 3). The proposed facility would provide the space
and capability for MOD to conduct the required IM testing on all conventional
munitions in the military inventory at a single location at WDTC.
3.3.4.1. The
proposed IM Test Grid would encompass an area of about 1,924 acres (see map on
Page 3). The proposed IM Test Grid would
be in large part non-exclusive in the sense that its use as an IM Test area
would be coordinated with WDTC Range Control and other test programs (Stryker,
JSLSCAD, JCAD, JSLNBCRS, etc.) which have used this area in the past and will
continue to use it in the future. The purpose of the larger IM Test Grid area
is to allow MOD to control ingress and egress during the relatively short
duration of an individual IM test.
3.3.4.2. Physical
alteration to the existing landscape would occur at three (3) generalized
locations on the proposed IM Test Grid (see map on Page 3):
·
Less than 1 acre
at the area surrounding the Control Point (CP).
This would include re-establishing electrical connections to the CP,
renovation and refurbishing the existing CP, removal of a sand berm adjacent to
the CP, and clearing and renovation of an existing gravel parking lot.
·
Less than 2 acres
in the form of a 164-foot radius circle cleared of vegetation located on either
side of an existing road a short
distance northeast of the CP for use a bullet impact test area. Additional work in this area would involve
depositing the sand from the berm adjacent to the CP into a new sand berm to be
placed across the road east of the 164-foot radius cleared area. Future work at this location (as need dictates
and funding permits) would include installation of a moveable gun mount on the
western side of the cleared area.
·
At its maximum planned
future dimension, a 2000-foot radius (288.5 acres) circle, cleared of
vegetation, would be established in the northeastern corner of the proposed IM
Test Grid. The actual cleared area would
be based upon the needs of individual IM tests. The 2000-foot radius maximum cleared
area would accommodate IM testing of the largest conventional munitions in the
current military inventory. It would
likely be a period of several years before the maximum cleared area would be
necessitated by IM testing requirements.
3.3.4.3. It is
also proposed that several of the access roads to the actual test areas be
upgraded by adding additional gravel or road base as project needs dictate and
funding permits. (It was mentioned
during the internal scoping meeting that large quantities of milled asphalt
from the re-construction of the Michael Army Airfield runway may be available
free of charge during 2006.)
3.3.4.4. The
drop tower presently located at the RADPAD would be moved and relocated to the proposed
IM Test Grid area as funding becomes available and future test requirements
dictate.
3.3.4.5. Solid
Waste Management Units (SWMU) and Hazardous Waste Management Units (HWMU)
3.3.4.5.1. Two
SWMU have been identified in close proximity to the area of the proposed
action. SWMU 117 lies within the area
proposed to cleared (see map on Page 3).
SWMU 117 has been closed and has been cleared for use by DEP. SWMU 118 has not been closed, but lies
outside the area of the proposed action. DEP has indicated that this SWMU would not
conflict with the proposed action [12 October e-mail from Gary Richins (WD-EN)
to Scott Reed (DEP)] . There are no HWMU
anywhere near the area of the proposed action.
3.3.4.6 This
EA evaluates and assesses the environmental issues and impacts of the proposed
action, in accordance with Section 651.20 Environmental Assessment, 32 CFR Part
651, Army Regulation (AR) 200-2 Environmental Analysis of Army Actions; Final
Rule, dated March 29, 2002. This evaluation
includes the potential impacts to human health and the natural environment. It
should be noted that the only action that triggers an EA rather than a record
of environmental consideration (REC) for this proposed project is the potential
for soil surface disturbance in excess of five (5) acres. Since the proposed
action has a potential soil surface disturbance of approximately 292 acres at
its maximum iteration, preparation of an EA was required in accordance with
(IAW) 32 CFR §651. This area was
previously (30-40 years ago) used extensively as a test grid.
3.3.4.7 This proposed
action alternative is responsive to the need to support additional enhanced IM
testing for the DoD requirement under the requirements of MIL-STD-2105 C and TB
700-2. It is also responsive to the need to bring additional testing business
to WDTC and DPG. This alternative is also in the best interest of the defense
of the
|
PROPOSED IM TEST GRID SITE SELECTION MATRIX |
||||
|
Selection Criteria / Alternative Sites |
Alternative A: No
Action RADPAD |
Alternative B: Playa/Mudflats |
Alternative C: DTTF (OBOD) |
Alternative D: Preferred Alternative V-Grid |
|
1. Sufficient Size to Accommodate
Present and Future IM Testing |
- |
+ |
+ |
+ |
|
2. DPG/WDTC Command Approval/Support |
+/- |
+/- |
+/- |
+ |
|
3. Cost to Upgrade |
- |
- |
+/- |
+ |
|
4. Serviceable Command Post (CP) |
- |
- |
- |
+ |
|
5. Electrical/Comm/Data Available On Site |
+ |
- |
- |
+ |
|
6. Adequate Roads |
+ |
- |
+ |
+ |
|
7. Controlled Access During IM
Tests |
+ |
+ |
+ |
+ |
|
8. Proximity/Compatibility w/Other
Tests and Test Facilities |
- |
+ |
+ |
+ |
|
9. Natural Resource Concerns |
+ |
+ |
+ |
+/- |
|
10. Cultural Resource Concerns |
+ |
? |
+ |
+ |
|
11. Regulatory/Permit Concerns |
+ |
+ |
- |
+ |
|
12. Security for Possible Classified Tests |
+ |
+ |
- |
+ |